Reagipssilo
ALTHAMMER passes sludge silos to SAICA
Date: 20.08.2011
ALTHAMMER passes the two sludge storage tanks to the customer SAICA Containerboard after only six weeks of construction.The two silos are each about 400m3 and have a flat bottom discharge to unsubscribe the heavy-body ingredients.
The manufacturing took place at the plant in Heidenheim in large components to ensure a quick and smooth installation at site.
Secondary fuel is stored in the two silos which will be fed in the combustion process of the power plant.
ALTHAMMER brought along his whole experience in the range of plant engineering and construction.